Photos: NBN Co trials vacuum trenching in Kiama Downs

By Ry Crozier on Feb 11, 2011 8:52 AM
Filed under Communications

How your underground lead-in might be dug.

View larger image A way to dig the lead-in trenches from the pit to the side of a house is by water blasting, ... View larger image Vacuum excavation uses a high-pressure water jet to turn the clay to mud, which is then sucked ... View larger image The truck is relatively quick to set up - about 15 minutes - compared to other excavation ...

See all pictures here »

NBN Co has provided a rare glimpse of its fibre network in the first-release site of Kiama Downs, revealing a trial of vacuum excavation for lead-in trenching to homes and its backhaul plans for the site.

Representatives of the company and its lead contractor Transfield said they would begin completion processes on the work on Friday, with a view to finishing work on March 3.

NBN Co was trialling excavation methods to dig trenches from the street to a premises-connected device (PCD) that is attached to each home.

Although traditional excavation was used for some sites, the company had also used water blasting – where a high-pressure water jet is used to loosen the ground, which is sucked out with a vacuum – on between 150 and 200 homes.

Water blasting or vacuum excavation was attractive because it did little damage to residents' lawns.

"People are most concerned about their rockeries, garden or paving," a site technician said.

"I don't think we've had complaints about the water jet technique."

Another test trenching method was the Grundomat, which involved "thumping" a path underground to the wall of the house.

Other parts of the Kiama Downs trial area used aerial cabling.

"Every [trenching] tool has its place," the technician said.

Backhaul links

The trial area had 16 fibre distribution hubs, each servicing a fibre distribution area of 288 houses.

NBN Co ran its backhaul from there to its fibre access node (FAN) at the Kiama exchange five kilometers away.

The backhaul of two cables ran mostly through Telstra conduits that were leased from the carrier. The space was not provided under the the $9 billion deal that NBN Co was finalising with Telstra.

From the FAN site, traffic will run on a transit cable to a Nextgen interconnection point near Wollongong, to take back to NBN Co's interim point of interconnect (PoI) in the Global Switch data centre in Ultimo, near Sydney's CBD.

NBN Co revealed to iTnews that it is exploring deployment routes for a diverse backhaul feed into the trial area for redundancy purposes.

Talks were underway with rail and utility infrastructure owners on the possibility of running the fibre on their existing infrastructure routes.

Site safety

It took 126,000 work hours to get to this point at the site but the companies were proud it was done with no time lost to injury or need for medical treatment.

Of the 406 inductees to the work site, 32 were let go because they broke occupational health and safety rules.

About half of the subcontractors working at the Kiama Downs site were from the Illawarra region, which encompassed Kiama and its neighbours Shellharbour and Wollongong.

 
Follow us on Facebook and Twitter
 

Copyright © iTnews.com.au . All rights reserved.

 
 
 
 
 
Top Stories
Here's what the Dicker Data mega-merger means in dollars
Distie to report $200 million jump in revenue.
 
Office 365 hiring coup for Brisbane gold partner
Million-mailbox Microsoft migration expert goes channel.
 
 
Sign up to receive CRN email bulletins
   FOLLOW US...
Polls
Which mobile device couldn't you live without?


Latest Comments