Global Switch in high gear for Level 7 fitout

By Ry Crozier on May 23, 2011 12:46 PM
Filed under Cloud

Stulz CRACs support higher density suites.

Global Switch said it has almost completed the fitout of level 7 of its Sydney data centre.

Project Manager Andrew Ball revealed that the fitout had been completed in stages with the "final handover" due in about March 2012.

When completed, Global Switch intends for level 7 to house four suites and a combined total of approximately 4,000 square metres of technical floor space (i.e. excluding plant).

Level 7 was different to other floors in the flagship facility because it supported average floor densities per square that were between 10 and 15 percent higher than on lower floors.

It was also the first floor in the building to use chilled water computer room air conditioning (CRAC) units made by Stulz.

"There's a relatively high power density in the suites, to the point where we needed [CRAC] units to provide maximum cooling for that scenario," Ball said.

"The Stulz unit provided the greatest cooling capacity for its footprint. The ratio of space versus cooling capacity was quite favourable."

Global Switch had bought 63 ASD1600 CyberAir 2 CWU precision units from Stulz.

Each unit had to support a cooling capacity of 114 kW, but was rated by the manufacturer to perform at up to 165 kW, according to a product brochure [pdf].

The buy was partly influenced by "favourable results" from a study of the technology in Global Switch's Paris2 data centre (launching later this year).

Stulz units have also been installed in Global Switch's Singapore data centre; however, level 7 Sydney was the first time the technology had been used by the data centre operator locally.

Specialist equipment placement contractors were brought in to maneuver the CRAC units into position on the floor. The units were able to be transported to level 7 using an internal goods lift.

Ball said the placement didn't involve a lot of resources, but connecting the CRAC units required mechanical engineering and building management system (BMS) skills. Global Switch did not sub-contract fitout work to third parties.

He said Stulz won praise from Global Switch for getting its systems in place within a tight timeframe for the stage one build of level 7.

Major customer wins for Global Switch in the past six months included Department of Defence and NBN Co; however, Ball said he could not reveal whether either was housed on level 7.

 
Follow us on Facebook and Twitter
 

Copyright © iTnews.com.au . All rights reserved.

Global Switch in high gear for Level 7 fitout
 
 
 
 
 
Top Stories
More hope for desktop PC market
Workstation shipments to jump, even though PCs down overall.
 
No easy fix to crisis in PC repair
The strife at NCSS and AWA is part of a structural problem.
 
Oracle's Larry Ellison steps down
Co-founder to move aside after 37 years.
 
Sign up to receive CRN email bulletins
   FOLLOW US...
Polls
My business strategy is to:

Latest Comments
CRN Magazine

Issue: 330 | August 2014

CRN Magazine looks in-depth at the emerging issues and developments for the channel, and provides insight, analysis and strategic information to help resellers better run their businesses.