Powerlink Queensland partners with Atturra on SAP incident management system
Improves incident, risk and hazard management and is built with native SAP integration.
Powerlink Queensland has partnered with Atturra to implement a new network incident management system (NIMS) and will provide support until 2030 and beyond.
Powerlink services more than five million Queenslanders and 241,000 businesses through a 1,700-kilometre network that extends from Cairns to New South Wales and includes 15,449 circuit kilometres of transmission lines and 152 substations.
It’s the first in a new generation of network incident operating systems in the electricity sector in Australia and was reportedly a significant undertaking for Atturra.
“[This] has been one of the largest, most technically complex projects ever delivered by Atturra,” said Alastair Brooke, GM safety solutions, Atturra.
Transforming incident management with SAP
The new system replaces two-decade-old legacy systems and databases and has been modernised onto SAP S/4HANA, simplifying database and data management and supporting secure, highly available insight-driven applications.
It’s natively integrated into Powerlink’s SAP asset management platform and is built on SafetySuite for SAP, extended by custom SAP applications and powered by SAP Fiori Launchpad, SAP Business Technology Platform (BTP), OData (Open Data Protocol) services and Esri ArcGIS integration for spatial data mapping.
The system includes an intelligent smart search tool for system-wide visibility, an unplanned outage app for root cause traceability and automated notification workflows.
The design supports network incident, risk and hazard management that’s intuitive for field and control room users, while improving visibility, traceability and real-time safety management.
“NIMS enables us to more efficiently communicate incident management activities across all of the people that play important roles in keeping our network and assets safe, secure and reliable,” a Powerlink spokesperson said in a statement.
A new foundation for electricity networks in transition
The project is part of Powerlink’s Next Generation Network Operations program and supports its goals to deliver cost-effective, safe and reliable transmission services, while improving visibility and decision-making across incident, hazard and risk management.
“It has established a strong foundation for consistent, transparent, and data-driven decision-making, while positioning us to continuously improve how we identify, assess, and manage risk into the future,” a Powerlink spokesperson said in a statement.
It comes as electricity transmission providers look to modernise operational technology to incorporate renewables and adapt to challenging external conditions.
“We partnered with Powerlink to reimagine its business, ensuring that its next-generation IMS would be future fit to meet the organisation’s reliability goals as the network transitions to a greater mix of renewables and is challenged by increased volatility and fragility,” Brooke ended.